CTA

CTA RED LINE/DAN RYAN EXPRESSWAY TRAFFIC UPDATE FOR THE WEEK OF JULY 25 – AUGUST 1

July 22, 2004
7/22/04

Motorists who travel the Dan Ryan Expressway and CTA Red Line customers will experience minimal impact while work is underway on the Chicago Transit Authority's $282.6 million Red Line rehabilitation project.

CTA construction plans call for the periodic use of the left lane and shoulder of the expressway in both directions, and involve a combination of lane shifts, temporary ramp closures and by-pass tracks at eight work zones between Cermak Road and 95th Street. The work schedule is subject to change due to weather or unforeseen issues.

Traffic impact for the week of July 25 ? August 1 will be:

LANE SHIFTS:Lane shifts are in place northbound between 96th and 92nd Streets. Southbound lane shifts in the same location are scheduled to begin Monday, July 26. Lane shifts will be in place until early October.

Lane shifts continue in both directions between 42nd Place and 46th Place until the first week of August.

Lane shifts continue in both directions between 30th and 34th Streets until late August.

Lane shifts continue in both directions between 58th and 62nd Streets until early September.

TEMPORARY RAMP CLOSURE:The northbound 95th Street entrance ramp is temporarily closed until late October. Motorists are encouraged to use the entrance ramp at 87th Street.

NIGHTTIME ONLY LANE CLOSURES:The northbound left driving lane will be closed intermittently from 8 p.m. until5 a.m. at 45th Street until the first week of August and at 63rd Street until late August.

Nighttime only closures will continue intermittently through the fall.

BY-PASS TRACKS IN SERVICE:CTA trains are using by-pass tracks between 58th and 62nd Streets until late August.

CTA trains also are using by-pass tracks between 30th and 34th Streets until mid-September.

Customers will continue to board trains at their normal stations.

PROJECT SUMMARY:The Dan Ryan branch of the Red Line runs down the middle of the Dan Ryan Expressway and includes nine stations from Cermak-Chinatown to 95th/Dan Ryan. When the rehabilitation project concludes in winter 2006, the CTA will have improved signal, track, communications and power substation systems, renovated seven Red Line stations from Sox-35th to 87th Street and rehabilitated the bus bridges at 69th and 95th Streets.

# # #
Back to news