RPM construction has begun

RPM Phase One Project overview: 2021

Better CTA service is coming! We've broken ground on the transformational Red and Purple Modernization (RPM) Phase One Project. The modernization project has many steps, and it is important to know when and how you or your business may be affected.  Sign up for construction impact alerts in your community here. Click here for Construction Activity Notices related to this project.

Red-Purple Bypass, four-week project lookahead, July 16, 2021

Lawrence to Bryn Mawr, four-week project lookahead, July 22, 2021

New! Interactive construction project map

Red-Purple Bypass

We broke ground on the Red-Purple Bypass bridge in October 2019. The bypass will be completed in 2021 and will carry Kimball-bound Brown Line trains over Red and Purple Line tracks north of Belmont, easing train congestion and improving service for our customers.

After we finish the bypass, we will begin rebuilding the century-old Red and Purple Line tracks underneath the bypass, between Belmont and between Cornelia and Newport. The new Purple and Red Line tracks are expected be completed by the end of 2024, providing a smoother and more comfortable ride for our customers. See the latest construction activity notices by clicking here.

Red-Purple Bypass track foundation construction, November 2019

Lawrence to Bryn Mawr Modernization

We began the first of two stages of construction -- Stage A -- for the Lawrence to Bryn Mawr station and track reconstruction project in May 2021. 

Beginning in Spring 2021, activities will include the demolition of stations, track bridges and structure and partial embankment; construction of new track foundations; and the construction of the new bridge via a gantry system. Stage A rebuilds the northbound CTA Red and Purple Line tracks and will be completed in late 2022. Then, we will begin Stage B and rebuild the southbound Red and Purple Line tracks. That stage will be completed by the end of 2024.

See the latest construction activity notices by clicking here.

Advance utility relocation work and property demolition

In 2018, we began the pre-construction phase of Red and Purple Line Modernization (RPM) Phase One, which included property demolition and relocation of utility lines and equipment. It was necessary to complete this work before we could begin major construction of RPM Phase One work, which will include rebuilding four Red Line stations (Lawrence, Argyle, Berwyn and Bryn Mawr and adjacent track structure as well as constructing a new Red-Purple Bypass (RPB) north of Belmont station. The major construction work for Phase One began October 2019 and will be fully completed in 2025. 

We expect to substantially complete advance utility relocation work in early 2021. Property demolition work was substantially completed in 2019. 

 

Construction activity notices (CANs)

As we work hard to modernize the system for our riders, we know that our construction can and does affect people who live and work nearby. This is why we provide advanced notice to communities in the RPM project footprint about work that we will be doing. Construction Activity Notices (CANs) that we have issued for RPM Phase One work can be found here (scroll down the page). They are also emailed to affected residents and businesses and physically posted in work site areas.

 
 

Latest News

Embankment demolition work 08/02/2021

The work will require the alley west of N Winthrop Ave between W Ainslie and W Lawrence to be closed.​ Download Document

Bryn Mawr viaduct demolition 07/30/2021

W Bryn Mawr between N Broadway and N Winthrop will be closed for the weekend to allow crews to demolish half of the viaduct at W Bryn Mawr. Download Document

Crane lifts on W Ainslie 07/29/2021

W Ainslie between the CTA tracks and N Winthrop will be closed for crane activity. Download Document

Cable relocation and bracket installation work 07/28/2021

The work will intermittently blocks alleys behind 3433-3551 N Sheffield and 3500-3558 N Wilton as well as the lot west of 938 W Newport. Download Document

New track foundation drill shaft installation work 07/20/2021

There will be an extended closure of the alley behind 5700-5758 N Winthrop between W Ardmore and W Hollywood.​ Download Document

Embankment demolition and track-level barrier installation 07/19/2021

Track demolition and related work will block access to the alley behind 5100-5258 N Winthrop during daytime hours. Download Document

Track rivet removal work 07/19/2021

This work will require a closure of N Sheffield and traffic lane shifts on W Roscoe St. Download Document

Viaduct demolition 07/16/2021

W. Hollywood Avenue between N. Broadway and N. Winthrop Avenue will be closed to vehicular traffic. Download Document

Viaduct lighting modifications and installations 07/12/2021

There will be occasional parking lane closures on streets west of CTA tracks, including W Hollywood, W Bryn Mawr, W Catalpa, W Balmoral and W Berwyn. Download Document

Lead abatement and painting 07/12/2021

Work will effect traffic, parking and sidewalks at the intersection of N. Sheffield Avenue and W. Roscoe Street. Download Document

Results: 1 - 10 of 483 Articles

Note: The above includes only Construction Activity Notices related to the RPM Program as an added courtesy during the program, and does not include those related to regular maintenance to our structure or tracks, even in the area of where RPM work is taking place. Other types of Construction Activity Notices are distributed locally, only.