Construction Project Briefing June 2, 2010 Slide #2 Today’s Presentation • Cermak Station Project • Subway Escalators Project • Howard Signals Project • Loop Signals Project • Blue Line Signals Project Slide #3 Project Title: Cermak Station Project Managing Department: Facilities Construction * Justification of Need: Reconstruct station entrance after vehicle accident and fatality; make station fully accessible. * Priority of Project: High * Project Budget: $12.5M * Earned to Date: $5.9M * Percent Change Orders to Construction Contract: 0% * Percent Time Used to Date: 53% * Funding Source: ARRA (Federal Stimulus Funds) * Procurement Status: Archer auxiliary entrance is under construction. Will apply for permit in Spring 2010 for Cermak Station main entrance. * Estimated Start Date/Estimated Length of Project: Project started November 2009; 15 month duration * Project Manager: Steven Mascheri (GM), Chris Mulcrone (PM) * Overview of Scope: New auxiliary entrance at Archer Avenue, new station house with new revenue equipment, elevator, escalator, and bike racks at Cermak entrance, attain ADA compliance upon project completion. Slide #4 Project Title: Cermak Station Project Managing Department: Facilities Construction * Impact on Customers: Cermak entrance will be closed during construction. CTA will construct new Archer entrance to keep station open. * Benefit to System: Station will become ADA-compliant. Third means of egress from platform for station access & exiting * Benefit to Community: Station will become ADA-compliant. New Archer Avenue auxiliary entrance. * Impact on Accessibility: Station will become ADA-compliant * Estimated # of Jobs Created: 50 on-site jobs (Contractor, CM, PM) * Customer Communication Need: Cermak entrance to be closed during construction and will reroute customers to Archer auxiliary entrance * Comparable Projects: Brown Line Capacity Expansion Project Slide #5 Project Title: Cermak Station Project Managing Department: Facilities Construction * The design of Archer entrance has been completed and the permit was issued in December 2009. * The design of Cermak entrance is underway with 30% progress set of drawings issued. CTA departments are reviewing and providing comments to those drawings. Cermak permit is in for permitting with the City. * The construction of the Archer entrance began in November 2009 and the stationhouse steel was erected, the concrete walkway was poured and underground utilities were relocated. The platform was cut for the new stairway, electrical upgrades are complete, and fare control was delivered and installed. Scheduled completion date of the Archer entrance is 6/1/10. * At the Cermak main entrance, the damaged escalator was removed and the site is currently being prepped for new escalator, stairs and elevator. Electrical work is being finalized for the Archer Entrance. Scheduled completion date of the Cermak main entrance is 12/31/10. * There are no current delays on this project. Slide #6 Project Title: Cermak Station Project Managing Department: Facilities Construction * This picture shows Archer stationhouse having final pieces of equipment installed including doors, lights, CA booth, and fare control equipment. Slide #7 Project Title: Cermak Station Project Managing Department: Facilities Construction * This picture shows the structural steel in place for new staircase to platform and walkway to stationhouse. Slide #8 Project Title: Subway Escalators Managing Department: Facilities Construction * Justification of Need: Escalators beyond useful life; high maintenance cost * Total Project Budget: $22.8M * Construction Contract Value: $17.2M * Earned to Date: $15.1M or 92% * Percent Change Orders to Construction Contract: 3.98% * Percent Time Used to Date: 87% * Funding Source: FTA * Estimated Start Date/Estimated Length of Project: NTP 1/7/08; Completion date 9/22/10 * Project Manager: Bob Wittmann (GM), Rick Herndobler (PM) * Detailed Overview of Scope: Replace nine escalators, reopen one exit and relocate one escalator facility on the Red and Blue Line Subways Slide #9 Project Title: Subway Escalators Managing Department: Facilities Construction The following was work either completed or to be under construction: * Jackson/Van Buren Red (street to mezzanine escalator) was returned to service 2/19/09 * Monroe/Adams Red (platform to mezzanine escalator) was returned to service 3/19/09 * Adams/Jackson Red (street to mezzanine escalator) was returned to service 4/18/09 * Randolph/Washington Blue (platform to mezzanine escalator) was returned to service 5/4/09 * Adams/Jackson Red (street to mezzanine escalator) was returned to service 9/4/09 * Harrison Red (platform to mezzanine escalator) was returned to service 9/9/09 * Monroe/Adams Red (street to mezzanine escalator)was returned to service 9/28/09 * Monroe/Adams Red (street to mezzanine escalator) was returned to service 5/19/10. * Madison/Monroe Blue (platform to mezzanine escalator) is scheduled to return to service in August 2010. * Delay Explanation: No current delays. Slide #10 Project Title: Howard Signals Project Managing Department: Power & Way Construction * Justification of Need: Restore system reliability and improve performance of the train control system * Priority of Project: High * Total Project Budget: $7M * Construction Contract Value: $5.5M (Signal); $355K (JOC); $555K (Additional JOC work funded) * Earned to Date: $2.5M (Signal); $320K (JOC) * Percent Change Orders to Construction Contract: 0% * Percent Time Used to Date: 38% (Signal); 100% (JOC); 0% (Additional JOC) * Funding Source: CTA Bonds * Estimated Start Date/Estimated Length of Project: NTP issued 8/6/09; completion by 7/27/11. * Project Manager: Barney Gray (GM); Grace Ohs (PM) * Detailed Overview of Scope: o Upgrade existing Vital Processor Interlocking (VPI) systems at interlockings near the Howard Street Station. Upgrades to Communication hardware and software. Also includes replacement of faceplates for Howard Control Panel, new CTC Workstation and new Maintainer’s overview displays. o Project also includes supplemental JOC work at Howard Tower. Roof replacement, HVAC replacement, and new fire suppression system is included. o Additional $555K JOC work includes Jarvis wall and abutment repair and backup generators. Slide #11 Project Title: Howard Signals Project Managing Department: Power & Way Construction * Impact on Customers: During non-rush periods, reduced train speeds when workers are on the ROW. * Benefit to System: Improve signal system at Howard Interlocking to prevent delays to service. * Benefit to Community: More consistent travel times due to increased reliability * Impact on Accessibility: N/A * Estimated # of Jobs Created: N/A * Customer Communication Need: Courtesy notification to the Alderman and community about the project. Train announcements about reduced speeds due to workers on the ROW. * Comparable Projects: Blue Line Signals Project, Loop Signals Project Slide #12 Project Title: Howard Signals Project Managing Department: Power & Way Construction Construction Progress * Printed circuit boards were received. Installation of CSEX3 boards was completed in April 2010. Next field visit planned for September 2010. * Wight-Hill started work 6/10/09, HVAC and roof work is substantially complete. This portion of the project is in closeout. * There are no current delays on this project. Slide #13 Project Title: Loop Signals Project Managing Department: Power & Way Construction * Justification of Need: Upgrade Towers and interlocking control systems to current technology; Tower 18 past useful life * Total Project Budget: $103.2M * Construction Contract Value: $67.9M * Earned to Date: $50.6M or 74.5% * Percent Change Orders to Construction Contract: 40.7% * Percent Time Used to Date: 100% * Funding Source: FTA, RTA, Bond funds * Estimated Start Date/Estimated Length of Project: NTP 2/21/07; Original completion date 9/2009; Revised completion date 9/2010 * Project Manager: Barney Gray (GM); Brittany Dyra (PM) * Detailed Overview of Scope: o New Bi-directional Cab Signal System for the Loop o Construction of new Control Tower at Lake/Wells o New control panel with remote controls for Tower 12 and Jefferson o Installation of a new Signal Facility Building at Randolph/Wells o Installation of a new Tower 12 Relay House o Installation of new Interlocking at Jefferson Slide #14 Project Title: Loop Signals Project Managing Department: Power & Way Construction Construction Progress * Milestone 1- Approved Signal Block Design: Original completion date was 8/20/07, revised completion date was 4/2008, actual completion date was 3/18/08 * Milestone 2-Approved Cable Plan: Original completion date was 9/4/07, revised completion date was 5/2008, actual completion date was 5/21/08 * Milestone 3-Approved Tower 18 Circuit Design: Original completion date was 9/19/07, revised completion date was 6/2008, actual completion date was 12/2/08 * Milestone 4-Audio Circuit Cutover: Original completion date was 9/2008, revised completion date was not given, actual completion date was 9/14/08 * Milestone 5-Tower 18 Relay Room: Original completion date was 3/20/09, revised completion date was 11/09, actual completion date is still TBD * Milestone 6-Tower 18: This milestone can’t be started until Milestone 5 is complete. Original completion date was not provided, revised completion date is 5/2010, actual completion date is still TBD * Milestone 7-Tower 18 Interlocking: Original completion date was 8/2009, revised completion date is 9/2010, actual completion date is still TBD * Milestone 8-Tower 12 Interlocking: Original completion date was 8/2009, revised completion date is 10/2010, actual completion date is still TBD * Milestone 9- Substantial Completion: Original completion date was 9/2009, revised completion date is 10/2010, actual completion date is still TBD * Delay Explanation: o Original project schedule to be complete 9/2009; current project schedule shows completion for 9/2010. * NOTE: Signal Engineering completed two week factory testing of the new Tower 12 relay house in Batesburg, South Carolina. * Tower 18 Relay Room cutover was completed 11/16/09; testing still remains related to this milestone. Slide #15 Project Title: Blue Line Signals Project Managing Department: Power & Way Construction * Justification of Need: Signal system is beyond expected service life and upgrades needed for compatibility with new AC-powered rail cars. Traction Power upgrades needed to reduce power shutdowns and service disruptions. * Total Project Budget: $243M * Construction Contract Value: $185.6M * Earned to Date: $183.4M or 99% * Percent Change Orders to Construction Contract: 7.4% * Percent Time Used to Date: 100% of original time, 100% with new date of 11/22/09 * Funding Source: CTA Bonds, RTA, FTA, IDOT * Estimated Start Date/Estimated Length of Project: NTP 12/1/05; Original scope completion date 7/1/09, substantial completion date for additional work 11/22/09 * Project Manager: Barney Gray (GM); Grace Ohs (PM) * Detailed Overview of Scope: o Blue Line Signal and Traction Power Upgrades. o Replace and upgrade signals systems, power distribution, and associated components at various facilities in the Dearborn Subway, the Congress and Kennedy Branches of the Blue Line and State Street Subway. Upgrades to communication facilities to include new fiber optics and copper wiring and emergency telephones in the Dearborn Subway. Slide #16 Project Title: Blue Line Signals Project Managing Department: Power & Way Construction Construction Progress * Punch list work continues from Jefferson Park to Forest Park. * Automatic Vehicle Identification upgrades are ongoing. * Testing of 13th and 17th Towers started 1/25/10 and will continue for five weeks. Testing to be completed at the end of May 2010. * Delay Explanation: Contract Completion date extended from July 1, 2009 to November 22, 2009 for the completion of additional work. Final acceptance and punchlist items will continue after November 22, 2009.